On June, 2065438 1 day, hangzhou east railway station Railway Hub successfully poured the cast-in-place box girder of the first-hole double-track railway. It marks the official start of high-performance concrete mixing and supply production in hangzhou east railway station Railway Hub.
On September 8, 20 10, the first phase of the East-West Square Complex Project of hangzhou east railway station Hub started.
At around 10, 10, 19, 65438 in the morning, the first T-beam of the reconstruction and expansion project of hangzhou east railway station, a right-hand ramp bridge around Zhejiang and Jiangxi, began to be laid, which marked the official start of the T-beam laying work of hangzhou east railway station Management Department of China Railway Fourth Bureau.
10 2065438+65438 February +07 10, the first extra-large bridge of hangzhou east railway station reconstruction and expansion project, the Zhejiang-Jiangxi bypass upward rerouting bridge, was successfully erected, which successfully laid a solid foundation for the node goal of the whole line of Hangzhou Railway Hub East Station reconstruction and expansion project.
20 10 12 2 1 8: 00 am, the existing Desheng road overpass in the expansion project of Hangzhou Railway Hub East Station officially began to be demolished.
20 1 1 On March 9th, 2008, the newly-built high-performance concrete mixing station of Hangzhou East Project Group of China Railway Fourth Engineering Company No.2 was officially put into use, achieving the goal of winning the first battle.
2065438+01March 22nd, the steel structure project undertaken by Hangzhou Xiaoshan Southeast Power Grid Company has completed the steel structure construction at the west end of the station building, creating favorable conditions for the first-line transfer of high-speed rail.
In the early morning of March 3, 2011,8 existing lines of hangzhou east railway station expansion project undertaken by China Railway Fourth Bureau No.2 Company were successfully transferred to 3 new lines, marking the completion of the first transfer task of the East Station project during the year.
20 1 165438 On the eve of April 6, 2008, the hangzhou east railway station capacity expansion project, which was undertaken by the Second Company of China Railway Fourth Engineering Group, successfully converted nine lanes into four new lanes, marking the completion of the original track conversion task of hangzhou east railway station Railway Station.
On the morning of 2011April18th, the last beam slab on the east line of Shanghai-Hangzhou high-speed railway was laid, and the whole line from Shanghai Hongqiao to hangzhou east railway station was closed.
On May 30th, 20 1 1, Sun Jingmiao, director of the provincial development and reform commission, and Zhao Yan, deputy director of the provincial development and reform commission, made a special trip to the railway hangzhou east railway station hub project to carry out the service investigation of "Hundred Thousand Services".
On March 20th, 20 13, a signboard was hung at Hangzhou East Railway Station.
On June 26th, 20 13, the Hangzhou municipal government announced that hangzhou east railway station would be opened on July 6th, 20 1 3.
On June 30th, 20 13, tickets were officially sold to the public at 8: 00 am.
2065438+July 2003 1, officially put into operation.
On 2065438+65438 in04+6543810 +0, the West Plaza was put into use.