How long does the renovation period usually take?
Generally speaking, the construction period is from the commencement to the overall acceptance of the house. Take the small apartment of 100 m2 as an example, and the specific time allocation is as follows:

1. Demolition and reconstruction of main body. Including wall shoveling, slotting, wall shoveling, etc. About three days.

2, water and electricity disclosure. Coordinate the time between the plumber and the designer. Assuming one day's delay and one day's disclosure, the construction of hydropower pipeline will take about two to three days, assuming three days, that is, five days.

3. When the bricklayer comes into play, cement, sand, bricks and other materials shall be prepared one or two days before the play, assuming two days. Building pipes, columns, partitions, etc. About two days; Waterproof works for one day; Closed water test for two days. It takes seven days here.

4. Tiles. 100 square meter, it takes about 10 day for two bricklayers, three days for drying and curing after pasting, and thirteen days for * * *.

5. Cabinets, furniture, doors and windows will be measured on the spot, and the woodworking disclosure will be completed at the same time, which will take about one day.

6. After the oiler comes into play, the wall should be painted with putty and gray latex paint. Skilled workers need about twenty days to finish painting all the walls.

7. Customize cabinets and wardrobes. It takes about 25 days from measurement to completion. On the fifth day after the wall painting, the cabinets and wardrobes were customized and installed, which took about three days. It takes about eight days from the completion of the wall to the installation of the cupboard.

8. It will take about forty days to complete the wooden door measurement. It takes about three days to install wooden doors and skirting lines one week after the cabinet is installed.

9. It takes about three days to clean and install lamps, switches and sockets.

Total calculation time: 3+5+7+13+1+20+8+3+3 = 63.

Take the small apartment of 100㎡ as an example, construction will continue on holidays and weekends, during which there will be no other emergencies and it will generally not be so calm. If a certain material is not in place on time; Or the furniture comes into play later, causing bumps and needing maintenance; Coupled with the later acceptance work, as well as holidays and weekends are not allowed to disturb the people, basically it takes about three months from the completion of design to the completion of all construction.